Construction of Afghan National Police Head Quarter

 Contractor Name  Rixon Engineering & Construction Co.
Contractor Address Lane 5, street 15, Wazir Akbar Khan Road, Kabul Afghanista
Contract / Number: W5J9LE-12-C-0002
Contract / TO / PO Dollar Value: $ 1,300,000.00 USD
Contract / TO / PO Status:

 Complete

Percent (%) complete and schedule completion date (if active)

Completion date : 2012

Project Title: Tourgoundi Border Herat Province, Afghanistan
 Project Description:

The project was awarded to REC for“ Construction  of  Afghan National Police Head Quarter Herat Province Afghanistan ”  
Feature of work that REC completed, including the statement of the total dollar value in this work:  

  • Construction of Administration building  507m2
  • Construction of Women Barrack 48m2
  • Construction of Fuel Point
  • Construction of 20m high water tower 
  • Construction of septic and leach field 
  • Construction of security measure ( guard tower, security wall, guard shake, and fecne)
  • Construction of water system, power system and sewer system   


The subcontractor total Dollar value awarded and completed for this work was $ 1,300,000.00 USD 

 

 

Posted in Blog

Construction of CMU buildings of ANA Combat Logistics Battalion (CLB)

 Contractor Name  Rixon Engineering & Construction Co.
Contractor Address Lane 5, street 15, Wazir Akbar Khan Road, Kabul Afghanista
Contract / Number: W5J9JE-10-D-0017-0014 215TH CLB
Contract / TO / PO Dollar Value: $ 3,144,916.00 USD
Contract / TO / PO Status:

 Complete

Percent (%) complete and schedule completion date (if active)

Completion date: December, 2012

Project Title: Construction of CMU buildings of ANA Combat Logistics Battalion (CLB) Kandak and Transient Kandak
Location (City and Province)  Camp Shorab Helmand Provice
 Project Description:

The project was awarded to REC for

“Construction of CMU buildings of ANA Combat Logistics Battalion (CLB) Kandak and Transient Kandak, Helmand Province Afghanistan ”  


Feature of work that REC completed, including the statement of the total dollar value in this work:   


The subcontractor total Dollar value awarded and completed for this work was 3,144,916.00 USD

 

 

Posted in Blog

Construction of K-Span Building Ghormach Faryab Afghanistan

 Contractor Name  Rixon Engineering & Construction Co.
Contractor Address Lane 5, street 15, Wazir Akbar Khan Road, Kabul Afghanista
Contract / Number: W91B4M-11-R- 6521-500
Contract / TO / PO Dollar Value:  $380,000.00USD
Contract / TO / PO Status:

 Complete

Percent (%) complete and schedule completion date (if active)

Completion date 100% Completed 14 Dec 2011

Project Title:

Construction of CMU buildings of ANA Combat Logistics Battalion (CLB) Kandak and Transient Kandak

Subcontractor

Location (City and Province)  Faryab Afghanistan
 Project Description:

Construction 2 (25 x 10) K-Span Shell Construct at the Ghormach district ANA base,  
Faryab City, Afghanistan

a.  Subgrade  Preparation  of  Road (500)M2

b.  Slab  On  grade  for  two  K-Span Buildings

c.  Construction of two K-SPAN Building for ANA

 

 

Posted in Blog

Construction of K-Span Building Ghormach Faryab Afghanistan

 Contractor Name  Rixon Engineering & Construction Co.
Contractor Address Lane 5, street 15, Wazir Akbar Khan Road, Kabul Afghanista
Contract / Number: W5J9JE-12-C-0098
Contract / TO / PO Dollar Value:   $1,135,000.00USD
Contract / TO / PO Status:

 Complete

Percent (%) complete and schedule completion date (if active)

Completion date 100% Completed April 2014

Project Title:

Construction of K-Span Building Ghormach Faryab Afghanistan

Subcontractor

Location (City and Province)  Faryab Afghanistan
 Project Description:

Construction of 2 Story Afghan National Police Head Quarter Laghaman Province Afghanistan.

  • Construction of Administration building  507m2
  • Construction  of Women Barrack 48m2
  • Construction of Fuel Point
  • Construction   of   20m   high water tower
  • Construction  of  septic  and leach field i. Construction of  security measure ( guard tower, security wall, guard shake, and fence) 
  • Construction of water system, power system and sewer system

 

 

Posted in Blog

Construction of (ANA), 209th Corps Shaheen Fuel Farm Expansion

 Contractor Name  Rixon Engineering & Construction Co.
Contractor Address Lane 5, street 15, Wazir Akbar Khan Road, Kabul Afghanista
Contract / Number: W5J9JE-13-C-0002
Contract / TO / PO Dollar Value:  $2,533,175.00 USD
Contract / TO / PO Status:

 Complete

Percent (%) complete and schedule completion date (if active)

Completion date 100% Completed 15 Feb 2015

Project Title:

Construction of (ANA), 209th Corps Shaheen Fuel Farm Expansion

Primary Contractor

Location (City and Province)   Dehdadi District, Balkh Province, Afghanistan
 Project Description: 209th Corps Shaheen Fuel Farm Expansion: This solicitation is for a firm-fixed price contract to acquire construction services for the Afghan National Army (ANA), 209th Corps Shaheen Fuel Farm Expansion, Dehdadi District, Balkh Province, Afghanistan. This project is defined as the management, planning, design, labor, and equipment, to site adapt and construct all utilities, vehicular access, buildings, force protection measures, site security, and other features as referenced within Provide all labor, material, and equipment necessary to provide two (2) additional 94,500 liter generator fuel tanks in accordance with the requirements provided in Electrical Power shall be installed and commissioned to the new Fuel Oil Unloading Pump Skid, Fuel Oil Transfer Pump Skid, Fuel Oil Heater Skid, outlets and Fuel System Instrumentation Supply of the total 851000 liter   diesel  to fill all the 10 fuel storage tanks

 

 
 

 

Posted in Blog